Site Preparation

You must follow all safety and site requirements and instructions to properly set up, configure, and use the ECUTS.

Ensure the facility meets the following environmental, physical, and interface requirements before the ECUTS arrives.

ECUTS-16000 Environmental, Physical, and Interface Requirements


1378

Ventilation Clearances

The following clearances are required to ensure proper airflow to the ECUTS. Clearances are measured from the ECUTS test rack exterior and do not include the 9025TR platform or monitor arm. Ensure obstructions do not violate the following clearance requirements:
  • Top: 760 mm (30 in.)
  • Front and Back: 300 mm (12 in.)
Caution You must follow the ECUTS power dissipation and ventilation requirements to avoid thermal hazards.
Attention Vous devez suivre les exigences de ventilation et de dissipation de puissance du ECUTS pour éviter tout risque thermique.