Not every issue known to NI appears on this list; it is intended to show the most severe and common issues that you may encounter and provide workarounds when possible. Other technical issues that you may encounter could occur through normal product use or system compatibility issues. You may find more information on these issues in NI’s Product Documentation, Knowledgebase, or Community; see Additional Resources.

Bug Number

Legacy ID

Description

Details

1596248

Test Monitor does not attach large test reports to SystemLink

TestStand report files over 80 MB are not uploaded to SystemLink and attached to the corresponding test result.

Workaround:

Ensure your report files are smaller than 80 MB or transfer them manually.

Complete the following steps to ensure the report is unique to each DUT if you are using the batch process model:
  1. Navigate to Configure > Results Processing...
  2. Select the Options... icon in the Report row.
  3. Select the Report File Pathname tab.
  4. Configure the report to be created per DUT.

Reported Version:

Battery Test System Software Toolkit 2.0

Resolved Version:

N/A

Added:

Sep 1, 2021

1985043

The NI Battery Test System Web Server does not start properly in slow Windows computers

The NI Battery Test System Web Server windows service does not start properly and displays a timeout error in slow computers.

Workaround:

Increase the Windows service timeout value following the instructions here: A slow service does not start due to time-out error in Windows

Reported Version:

Battery Test System Software Toolkit 2022 Q2

Resolved Version:

N/A

Added:

Jun 27, 2022

2367972

Sometimes the Battery Test System Server incorrectly indicates a LabPC is still running

The Battery Test System Server may incorrectly assume that a Lab PC is still running after executing a test plan if you use one of the following functions:
  • Save & Run
  • Test Station > Test Plan Execution > Run Test

Workaround:

Manually check the status of the LabPC. If the LabPC is not actually running, then disregard the server’s indication.

Reported Version:

Battery Test System Software Toolkit 2023 Q2

Resolved Version:

N/A

Added:

Jun 5, 2024

2376473

Migrating from Linux to Windows may cause case-sensitivity compatibility issues

You may encounter errors when migrating from Linux to Windows if your file storage contains paths that only differ in letter case. Windows cannot create paths in this case because it treats paths as case insensitive. For example, Windows interprets ‘Foo’ and ‘foo’ as the same path.

Workaround:

NI does not recommend migrating back from Linux to Windows. If you need migration assistance, contact NI technical support.

Reported Version:

Battery Test System Software Toolkit 2023 Q2

Resolved Version:

N/A

Added:

Jun 5, 2024

2563231

Delay in updating the test station connection status in the Battery Test System Server UI

When a Lab PC is brought down, the test station connection status becomes disconnected within a few seconds. The test station connection status may take up to 10 minutes to update after bringing the Lab PC back online, despite frequent refreshing.

Workaround:

There is currently no known workaround for this issue.

Reported Version:

Battery Test System Software Toolkit 2023 Q2

Resolved Version:

N/A

Added:

Jun 5, 2024

2673574

Uploading large files through the Package Loader tab on the server's UI results in an error or page freeze

The Battery Test System Server has a maximum message size limit when uploading package files through the browser. When the message size exceeds the limit, the system closes the connection with an error. However, the system does not provide a detailed error message, and may leave the page unresponsive. This limit is calculated based on the formula:

s ≈ 80 + 3*(n-1) + c

where s is the message size in bytes, n is the number of files being uploaded, and c is the total number of characters in all of the relative paths of files selected to upload.

Workaround:

  • Reduce the number of files or shorten the file paths, then try uploading again.
  • Use the Battery Test System Package Loader from the command line interface.

Reported Version:

Battery Test System Software Toolkit 2023 Q2

Resolved Version:

N/A

Added:

Jun 5, 2024

Final Time Issue Listed

Issues found in this section will not be listed in future known issues documents for this product.

There are currently no issues to list.

Additional Resources

Explore Support Content and Product Documentation 

 

 

Ask the NI Community

 

 

Request Support from an Engineer

 

A valid service agreement may be required, and support options vary by country

 

Glossary of Terms

 

  • Bug ID - When an issue is reported to NI, you may be given this ID or find it on ni.com.  You may also find IDs posted by NI on the discussion forums or in KnowledgeBase articles.
  • Legacy ID – An older issue ID that refers to the same issue.  You may instead find this issue ID in older known issues documents.
  • Description - A few sentences which describe the problem. The brief description given does not necessarily describe the problem in full detail.
  • Workaround - Possible ways to work around the problem.
  • Reported Version - The earliest version in which the issue was reported.
  • Resolved Version - Version in which the issue was resolved or was no longer applicable. "N/A" indicates that the issue has not been resolved.
  • Date Added - The date the issue was added to the document (not the reported date).